22/02/2014-SITE MEASUREMENT AND ANALYSIS
Living Hall
13/03/2014-DEMOLITION AND DISMANTLING WORKS
27/03/2014-LAYERING NEW WATERPROOFING AT BATHROOM, BALCONY, YARD AND KITCHEN
17/4/2014-PLASTER CEILING INSTALLATION
25/4/2014-FLOOR RENDERING/ LEVELLING
12/5/2014-WALL AND CEILING PLASTER AND SKIMMING
15/5/2014-TILING WORKS AT ALL AREA
20/5/2014-CLEANING EXCESSIVE CEMENT GROUTING
23/5/2014-PAINTING WORKS
28/5/2015-AIRCOND AND ELECTRICAL FITTINGS INSTALLATION
13/6/2014-FINAL CLEANING AND HANDING OVER PROPERTY TO CLEINT