30/7/2012-DEMOLITION WORKS ON EXISTING PARTY/ SEPARATION WALL
15/8/2012-FLOOR RENDERING WORKS
19/9/2012-INSTALLATION OF PLASTER CEILING AND M&E FITTINGS
22/10/2012-FLOOR TILING INSTALLATION AND PAINTING WORKS
25/10/2012-BUILT-IN CONCEPTUAL DESIGN
24/11/2012-BUILT-IN FABRICATION AND INSTALLATION
27/11/2012-INSTALLATION OF POWDER COATED GLASS PARTITION