8/5/2013-PAD FOOTING AND COLUMN SETTING
29/5/2013-CONCRETING GROUND FLOOR SLAB AND R.C COLUMN
10/6/2013-FORMWORK ON FIRST FLOOR SLAB AND BEAM
15/7/2013-RAILING AND PAINTING WORKS
22/7/2013-INSTALLATION OF SNOOKER TABLE
1/8/2013-PROJECT COMPLETED
8/5/2013-PAD FOOTING AND COLUMN SETTING